Deadline to submit I-10 Project Comments - Sept 9

  • Woodland Heights Civic Association P.O. Box 7754 Houston, TX 77270 USA (map)

DEADLINE TO SUBMIT YOUR COMMENTS: August 26, 2022

To learn more, please visit our infrastructure page. You can also submit a comment directly to TXDOT using this link and providing the following project number: 0271-07-326
 

Key Details:

  • Project Purpose: Reduce the risk of flooding of the I- 10 facility and reduce occasions when the road would be impassable due to major rainfall events

  • Project Limits: From Heights Blvd. to I-45 (Approximately 1.8 miles)

  • Total Project Estimated Cost: Approximately $347 million

  • Anticipated Construction Start: Summer 2024

  • The project also includes the construction of a 21.7-acre detention pond located on the north side of I-10 between Taylor St. and Houston Ave.

  • Includes the construction of a 10-foot-wide shared use path on the north side of I-10 along White Oak Bayou between Studemont St. and I-45.